Very important information about Okha Dwarka Bridge
Gandhinagar: Gujarat government today said the Central government has given its approval to Rs 962 crore cable stayed signature bridge project connecting the coastal port town Okha and pilgrim town Bet Dwarka which is located on island.
The state government said it plans to complete this project in 30-month period.
Deputy Chief Minister Nitin Patel in his briefing at capital Gandhinagar today said that two million pilgrims who visit Bet Dwarka every year by boat in addition to 8,500 local people will benefit from this bridge project.
He said a 3.73 km four lane 27.20 meter wide cable-stayed signature bridge will be built connecting Okha and Bet Dwarka. The bridge will have 2.5 meter wide footpath with street lights. The footpath will have solar panels atop it which will generate 1 mw power. Approach of this bridge on Okha side will be 209 meter in length while on Bet Dwarka side it will be 1101 meter. Bridge portion length will be 2.32 km. 900 meter middle portion will be cable stayed type. Out of three spans the middle span will be 500 meter in length which will be the largest in India. It will have 150 meter toll two pylons. The other 13 spans on two sides will have 50 meter length.
Signature Cable Bridge Drone View: Click Here
The government conveyed thanks to Prime Minister Shri Narendra Modi for approval to this bridge project.
2320m long Okha–Beyt Dwarka Signature Bridge is an under construction cable-stayed bridge connecting Beyt Dwarka island in the Gulf of Kutch and Okha on Gujarat’s mainland.
Design
Okha–Beyt Dwarka Bridge with a length of 2320m will consist of a 27.2m wide deck with two carriageways. These will support 2 vehicular lanes and a 2.5m pedestrian walkway on either side with a 1MW solar mounted roof to provide shade. Its pylons will reach a height of 150m.
The bridge with 3 spans will have a 900m long central cable section and a 500m long middle span. The approach roads will be 209m long at Okha and 1101m long at Beyt Dwarka, making the entire project 3.73 km long.
The state government said it plans to complete this project in 30-month period.
Deputy Chief Minister Nitin Patel in his briefing at capital Gandhinagar today said that two million pilgrims who visit Bet Dwarka every year by boat in addition to 8,500 local people will benefit from this bridge project.
He said a 3.73 km four lane 27.20 meter wide cable-stayed signature bridge will be built connecting Okha and Bet Dwarka. The bridge will have 2.5 meter wide footpath with street lights. The footpath will have solar panels atop it which will generate 1 mw power. Approach of this bridge on Okha side will be 209 meter in length while on Bet Dwarka side it will be 1101 meter. Bridge portion length will be 2.32 km. 900 meter middle portion will be cable stayed type. Out of three spans the middle span will be 500 meter in length which will be the largest in India. It will have 150 meter toll two pylons. The other 13 spans on two sides will have 50 meter length.
The government conveyed thanks to Prime Minister Shri Narendra Modi for approval to this bridge project.
2320m long Okha–Beyt Dwarka Signature Bridge is an under construction cable-stayed bridge connecting Beyt Dwarka island in the Gulf of Kutch and Okha on Gujarat’s mainland.
Design
Okha–Beyt Dwarka Bridge with a length of 2320m will consist of a 27.2m wide deck with two carriageways. These will support 2 vehicular lanes and a 2.5m pedestrian walkway on either side with a 1MW solar mounted roof to provide shade. Its pylons will reach a height of 150m.
The bridge with 3 spans will have a 900m long central cable section and a 500m long middle span. The approach roads will be 209m long at Okha and 1101m long at Beyt Dwarka, making the entire project 3.73 km long.
Post a Comment